Foundation and shoring works on the Blueys Beach headland project

Blueys Beach headland

Foundation and wall piles for a headland renovation.

The site

A complex headland renovation required foundation piles, a garage shoring wall and later a crane base. Ground and rock conditions differed from those anticipated.

Our approach

Discussed the encountered conditions with the engineers and adjusted some of the wall piles to a soldier-pile arrangement. The Heavies later completed additional crane-base and stair foundation piling.

Builder: J Moore Builders. Engineer: Collins & Associates. Geotechnical consultant: Regional Geotechnical Solutions.

Read the complete project
The Heavies piling rig at the Stoney Creek Bridge abutment works in Pembrooke

Stoney Creek Bridge, Pembrooke

Cased bored abutment piles through fractured mudstone.

The site

Highly fractured mudstone, with reported core loss of up to 40%, complicated the abutment works. Piles at the second abutment needed to extend up to 4 m deeper than designed.

Our approach

Used the Mait HR75 to install 800 mm pile casings to rock-socket depth, extended reinforcement cages with specialist on-site welding, and completed the piles using tremie concrete placement.

Construction partner: ACG – Alliance Construction Group.

Read the complete project

Talk through your site.

Call Daniel Goodman with the location, scope and timing. Drawings and geotechnical information are helpful when available.

0404 481 004Email Daniel

Discuss mobilisation, access and the programme for your Mid-North Coast project.

Equipment & capability detailsTechnical resources